The furniture is ready and the site is not: where it goes and who pays

It is the most common situation on the whole contract, and almost no order provides for it: production has finished, the date was the date, and the building is not ready to take anything. From that moment somebody is holding somebody else’s goods, and it is worth knowing who.

In short. When the site slips and production does not, there are four routes: keep the goods at the maker’s, move them to a third-party warehouse, store them on site, or slow the deliveries down into phases. They cost different things and they move the liability to different places. The three lines that settle ninety per cent of the arguments are not about the price of storage: they are about how many free days are included, who has custody of the goods, and which document gets signed in place of delivery.

Why it happens almost every time

A hotel opens on two programmes running on different tracks. The first is the building’s, which depends on trades, consents, services and finishes, and which by its nature moves forward. The second is the furniture supply’s, which in order to open on time has to start long before the building is recognisable — drawing approved, prototype, samples, production — and which is the subject of the <a href="/en/guides/hotel-ffe-lead-time">guide on when to order the furniture</a>. The two programmes meet exactly once, on the delivery date, and for that date to hold the more rigid one has to give: production is finished and waits.

Buyers notice late because there is no line about any of this in the order: there is a delivery date, written as though it were a one-way promise, and nothing that says what happens if the date arrives and the place does not. The mistake is not the slippage, which is normal: it is not having decided in advance who holds the goods while everyone waits.

The four routes, and what each one costs

It stays at the maker’s. The safest option for the pieces: they stay where they were made, in a known environment, in their own crates, with the people who built them on hand for a touch-up. It has a physical limit, because a finishing department is not a warehouse and the space a hundred rooms take up is the space the next contract needs: that is why the free days are few and are stated up front.

It goes to a third-party warehouse. This is the route for large supplies: an operator receives, checks, stores and delivers on call. It separates the dates — the supply closes, the site draws the pieces when it needs them — and it has two costs to look at together: the rent, and the extra handling, which is when damage actually happens.

It is stored on site. This looks free and is not. A corridor, a room, a garage: dust, moisture off the screeds, other trades passing through, no dedicated key. Two weeks later a corner is marked and «whose fault is it» no longer has an answer, because nobody wrote down who had that area; this is where this guide meets the one on fitting furniture on a live site. If it is done, it is done with a record: room, date, condition of the space, who holds the key, for how many days.

It is delivered in phases. This is not a way of storing: it is the way of not having to. Floor by floor, block by block or by product family, with a date per phase instead of one for everything. It needs somebody to set the sequence and hold it, and it is the only one of the four that reduces the risk rather than moving it.

What standing still does to the materials

«Standing still» does not mean «safe», and bespoke furniture is not inert stock. Solid timber moves with the humidity of the air: in a building that has just been plastered, with the screeds still drying, the relative humidity is far higher than the humidity the piece was built in, and a door stacked flat takes the shape of whatever it rests on. Upholstery suffers weight: a cushion compressed for months does recover its shape, but not always and not at once, and leather marks where it is folded against an edge. Crates are made for transport, not for six months of stacking.

Then there is the part nobody looks at, and which is lost first: the label, the photograph and the schedule reference that say where that piece goes, with the paperwork that travels with it. A phase handled twice by people who did not receive it arrives at installation with no correspondence between pieces and rooms, and installation stops for an administrative reason. What has to travel with the goods is in the <a href="/en/guides/hotel-furniture-documents">guide on the documents</a>.

Who has custody, and why the word matters

As long as the question is «where are the goods» the subject is logistics; when the question becomes «who has custody» the subject is the thing that counts. Whoever has custody actually holds the goods and can control who gets to where they are, and that is who answers for damage that happens while the goods are there. Who owns them, who has paid for them and who made them matters less at that moment.

Two practical consequences follow. If the goods stay at the maker’s beyond the days included, it has to be clear that from that date they are held on the client’s behalf, and on what terms. If instead they enter the site before installation, custody passes to whoever runs the site: not a penalty, but the condition for being able to say, once damage has happened, who held the key.

Delivery of the goods, or delivery of the installed work

The most expensive misunderstanding in the whole sequence is one word used for two different things. Delivery of the goods happens when the pieces arrive and the note is signed: it says the goods are there and in what condition. Delivery of the work happens once installation is finished: it says that what was ordered exists in the place it was meant to exist. When the site slips the two drift months apart, and signing the second on the strength of the first means accepting a work that does not yet exist, with everything acceptance carries with it: the point from which time limits run, the final payment, the start of the warranty. On the first point there is the <a href="/en/guides/furniture-handover-report">guide on the handover report</a>; on the second, the one on final payment between delivery and acceptance. Two documents, two dates, two signatures — and in between a third most people skip: the storage handover record, one sheet with three photographs and a date, which fixes the condition of the goods on the day custody changes hands.

The lines to put in the order

Seven items that cost nothing while negotiating and cost a great deal if they are missing:

  • how many days of storage at the maker’s are included in the supply, counted from notice that the goods are ready;
  • what happens beyond those days: where the goods go, who moves them, at whose cost;
  • who has custody in each phase, named phase by phase and not in general terms;
  • who covers damage during storage and during transfers, and up to what limit;
  • two separate deliveries, goods and installed work, each with its own signed document;
  • the storage handover record, with photographs and a date;
  • the right to deliver in phases, and who sets the sequence;
  • who reports the slippage, to whom and with how much notice: a date that moves two weeks ahead of time is a programming problem, the same date moving the day before the lorries leave is a money problem.

How not to get there

A site cannot be stopped from slipping. Slippage can be made bearable, with three choices made at the start: set the delivery sequence when the order is signed, because a supply split into three phases absorbs two months of delay without anything stopping; bring forward the decisions rather than the production, because approvals, prototype and samples take up no space whereas finished pieces take up space and get damaged, and that is what the mock-up room exists to settle; state the included storage days early, because a number written into the order, however small, keeps the negotiation from happening with the goods standing still.

How we work

We have produced in our own workshops since 1982, and prototyping, sampling, production and logistics are all in the same manufactory: that is why a date for entering site moves once and not three times, and why the party answering for that date is the party that made the piece. We state four to eight weeks of production from approval, prototype included, and we deliver hotels of more than a hundred rooms to the times required, in phases where needed, both directly and on behalf of furniture general contractors. Every piece leaves in its own crate and arrives with a label, a photograph and a schedule reference, with the documentation broken down by product family: that is what lets a phase stay identifiable even after a spell in a warehouse. The terms are set out in full in our answers to studios’ questions. On a hotel contract the most valuable thing is time: products that comply, are certified and arrive on time mean opening sooner, and a hotel that opens starts earning. For a contract supply the route is the contract division.

Who pays for storage when the site slips?

Whoever the order says, and if the order says nothing the argument starts with the goods already standing still. What works is a written threshold: a number of free storage days included in the supply and, beyond those, a condition known in advance. Writing it in while negotiating costs nothing.

Can production be postponed instead of storing the goods?

Sometimes, and where it is possible it is the better route: no storage, no double handling, no risk of knocks. But a production slot is not held empty, and postponing by a month does not mean delivering a month later. It has to be decided early, not when the pieces are already being checked.

Does the warranty still hold if the goods sit in a warehouse for six months?

A warranty covers the product, not the storage: damage from storage is not a manufacturing defect. That is why what matters is the delivery date, the condition the goods were delivered in and who had custody of them, which are three things written on a signed document. On which regime applies to the supply there is the <a href="/en/guides/hotel-furniture-warranty-supply-or-works">guide on the warranty</a>.

Is it better to take one delivery or several?

Phased, wherever the building allows it: floor by floor, block by block, or by product family. Less stock stands still, the first rooms are fitted while the last are still in production, and a mistake shows up on the first phase instead of on a hundred rooms.

Talk to us The contract division

This page sets out assessment criteria and working practice; it quotes no prices, no lead times and no company case studies. The practical indications have to be checked against the actual case, because they depend on the contract, the building and the project. No technical standard is cited: requirements change with the intended use of the rooms.