Does the furniture arrive assembled, or is it put together on site?

On a hotel project the question looks like logistics, and in fact it settles the result: a carcase closed in the workshop and the same carcase closed in a corridor are not the same piece.

In short. Upholstery arrives finished, because it does not come apart. For fitted wardrobes, beds, counters and panelling the choice does exist, and it is not made on the cost of transport: it is made on the access route, on the tolerances of the building and on who answers for the finished piece. Assembled in the works means checked and tested before it leaves; built on site means it goes up the stairs, but also that the work is done on a floor that is not a bench. One rule holds: only what has been designed to be assembled on site is delivered knocked down, and it is assembled by whoever made it.

Why a piece assembled in the works is not the same piece

In a workshop a carcase is closed on a level bench, with the squaring checked and the doors adjusted with the piece standing still; then the movements are tried, it is cleaned and it is packed after testing. On site the same carcase is closed on a floor that is rarely level, in the dust of other trades and with no bench to work on. This is not about the skill of the fitters: a bespoke piece lives on small tolerances, and a carcase closed out of square gives doors that do not line up and drawers that do not run alike. What depends on the piece and what on the room it was assembled in we set out in the guide on a warped door.

The second reason is the surfaces. Every joint made on site is work carried out a hand's width from a polished top or a veneer. In the works the same joint is made before finishing, and whatever gets marked is taken back on the bare piece.

When knocked-down delivery is the right answer

The good reasons are few, and they are all physical or to do with the site:

  • the assembled piece will not go in: narrow stairs, small lifts, a landing with a turn in it. This is the commonest case in hotels made out of historic buildings, and it is measured beforehand — the subject of the guide on furniture that will not fit up the stairs;
  • the assembled piece would not exist: a ten-metre counter, continuous panelling, a headboard running the length of a wall are made to be put together in place;
  • the assembly has to follow the building: anchored elements, closures against walls that are off plumb, junctions on a floor with a varying level. Here the site joint is the right way to do it, not a compromise;
  • the site is handed over in phases: floors or blocks released at different times call for a supply that comes in more than once.

Outside these cases, delivering knocked down moves work from the workshop to the site — from the place that is equipped for it to the place that is not.

What stays assembled in any case

Some things are not a choice. Upholstery — sofas, armchairs, seating, upholstered headboards — is made finished: the frame sits under the padding and the covering, and opening it is not a site operation; at most these pieces travel without their feet or cushions. The same goes for small items and for anything whose assembly needs workshop equipment. If closing a piece takes a tool that lives in the factory, that piece is not delivered knocked down.

What site assembly asks of the site

Site assembly does not need much, but what it needs it really needs, and it is hardly ever in the order:

  • a clean area that locks, is lit and has a power point, big enough to open the packs;
  • the rooms finished where the piece is fixed: floor laid, walls finished, skirting decided. Assembling before that means assembling twice;
  • a sequence agreed with the site management, because a unit fixed to a wall ahead of the services becomes an obstacle for whoever comes next;
  • somebody to collect and remove the packaging: after a floor has been assembled, the cartons and pallets are a real volume.

Which safety regime and which documents apply to a team coming in to assemble depends on whether that area is still a construction site or has already been handed over: that is the subject of the guide on fitting furniture on a live site. If instead the furniture is ready and the site is not, the problem moves to storage — see the guide on furniture ready and the site not ready.

Where the risk changes hands

This is the part nobody looks at while negotiating and everybody pays for later. An assembled piece is accepted by eye: a scratch is there or it is not, and it shows on the day of delivery. A knocked-down piece arrives as a number of packs and becomes furniture only later, on a day that may be weeks away. In that interval the packs are somewhere, and that is where nearly all the disputes begin: a marked corner, a panel leaned badly, a pack opened out of curiosity.

This is why the two handovers are kept apart, with two documents: delivery of the materials, signed against the packs, and delivery of the assembled work, signed once assembly is complete. What the report has to say is in the guide on the handover report, and the difference between delivery and acceptance in the guide on the final payment.

There is also a risk specific to knocked-down supply: the missing pack. A box of hardware left on the lorry does not hold up one piece of furniture, it holds up the assembly of a whole floor, because the team is there that day. The useful check at delivery is not whether the packs look undamaged: it is counting them against the list and checking the accessory boxes one by one.

The lines to put in the order

Six items that cost nothing while negotiating:

  • which items arrive assembled and which knocked down, item by item;
  • who assembles: the supplier with its own fitters, the main contractor, or a third party appointed by the client;
  • who answers for the packs between delivery and assembly, and where they are;
  • the conditions the room has to meet on the day of assembly, written as conditions and not as hopes;
  • who takes the packaging away, and when;
  • two documents: delivery of the materials and delivery of the assembled work.

These lines are written into the order, not at delivery: the project calendar is in the guide on when to order the furniture, and the survey that says whether a piece will go in is in the guide on measurements.

How we work

We have worked in Brianza since 1982 and we have wood, marble, metal and upholstery work in house: the choice between assembled and knocked down is made at the drawing stage, not at delivery. Upholstery leaves our factory finished; elements that cannot leave assembled, for access or for size, are designed to be put together in place, with the joints set by the drawing rather than improvised, and they are assembled by the people who made them. On a hotel project the most important value is time: products that comply, are certified and are delivered on time mean a fast opening, and a hotel that opens starts to invoice. Which documents have to arrive with the furniture is in the guide on documents; the work we do is in the collections and project supply in the contract division.

Frequently asked questions

Does knocked-down delivery save money?

On transport and on volume it does, but site assembly is work, with a team, a duration and a risk of its own: the saving is not automatic and has to be compared case by case. The sensible basis for the choice stays the technical one — if the piece goes in assembled, it is sent assembled.

Who should assemble bespoke furniture?

Whoever made it, or a team working to its drawing and instructions. Assembly handed to a third party without the assembly drawing is the quickest way to turn a fitting fault into a dispute about the supply.

Can a piece assembled on site be taken apart and moved?

It depends how it was thought out. Elements designed for assembly in place have demountable joints and can be opened again; a carcase closed with glued joints cannot, and trying ruins it. Ask beforehand if the building expects pieces to be moved.

What is checked when the packs are delivered?

The number of packs against the list, the labels, the presence of the hardware and accessory boxes, the condition of the packaging, and a photograph of anything marked. A missing pack found on assembly day stops the team; found at delivery, it does not.

Talk to us The contract division

This page describes practice in design, in the workshop and on site; it quotes no prices, no lead times and no company cases, and it cites no technical standards. Which elements of a supply can be delivered knocked down, and on what terms, are matters for the design and the contract, to be checked on the actual job.